• Scope of Works

    Mechanical & Electrical Contractor

  • Client

    Bausch & Lomb

  • Value

    €16,500,000

  • Duration

    18 Months

  • Architect/Design Certifier

    Diarmuid Rial Architects

  • Consulting Engineer

    Synergy Engineering & Prochem Engineering

  • Main Contractor

    Walls Construction

Bausch & Lomb Area 9.1 Extension incl. IPA / RTO Central Plant

Weltec Engineering delivered the complete mechanical and electrical installation for the Area 9.1 extension at Bausch & Lomb in Waterford — a €16.5 million contract completed over 18 months as Life Science M&E contractor on a campus that stayed in full production throughout.

Project overview

Area 9 is a multi-functional complex on the Bausch & Lomb Waterford site, combining contact lens production, life science manufacturing, research and development, and surgical support. The Area 9.1 project extended that facility and added a new central plant serving the IPA and RTO (regenerative thermal oxidiser) systems.

Weltec was appointed by main contractor Walls Construction as M&E contractor for both the mechanical and the electrical packages, working to a design by Diarmuid Rial Architects with Synergy Engineering and Prochem Engineering as consulting engineers.

Mechanical scope

The mechanical package covered the full services infrastructure for the extension and its new central plant:

  • Chiller and process cooling systems
  • Low pressure hot water (LPHW) distribution
  • Steam and condensate
  • Purified water and IPA distribution
  • Medical gases and domestic water
  • Above and below ground drainage
  • HVAC and RTO exhaust
  • Plant structural support steel and access platforms
  • BMS and process controls

Electrical scope

Delivering both disciplines with one site team removed the mechanical–electrical interface risk that can drive delay on life science fit-outs. The electrical package included:

  • Electrical distribution boards and small power
  • General services and lighting
  • Communications and data containment
  • ATEX installation in classified IPA areas
  • HVAC and plant commissioning
  • Temperature and humidity mapping
  • Room validation

Working as a life science M&E contractor on a live site

The surrounding facility remained in production for the duration of the contract. Every tie-in to existing chilled water, steam, purified water and electrical distribution was planned around manufacturing schedules, with shutdown windows agreed weeks ahead and executed to the hour.

Off-site fabrication of pipework spools and plant skids in Weltec’s own workshop cut hot works and man-hours in the live area, and allowed quality checks to be completed before anything reached site — the approach we bring to every project.

Commissioning, mapping and validation

Commissioning covered HVAC and plant systems across both packages. Temperature and humidity mapping was carried out for the new manufacturing and storage areas, followed by room validation confirming that classified spaces held their design conditions under load. Mechanical and electrical results were issued as a single validation pack — one of the practical advantages of appointing a single life science M&E contractor for both disciplines.

BMS and process controls were integrated with the existing site systems, allowing the new central plant to be monitored and sequenced from the platform the client already operated, rather than running as a standalone island of plant.

Inside the IPA and RTO central plant

A central plant of this type carries the utilities a lens manufacturing hall depends on. IPA (isopropyl alcohol) distribution has to run in fully welded, traceable stainless pipework into ATEX-classified areas, with the electrical installation zoned and certified to match. The regenerative thermal oxidiser exhaust handles solvent-laden air from the process, so duct routing, support and thermal movement all have to be resolved alongside the structural steel and access platforms that carry them.

Purified water, steam and condensate, medical gases and process cooling each bring their own material, jointing and testing standards, and each has to be tied back into an existing campus distribution network. Grouping all of it into a single M&E contract keeps those interfaces, the testing regime and the validation documentation under one point of responsibility — the main reason clients appoint one specialist M&E contractor rather than splitting the packages.

Talk to us about your life science and pharmaceutical M&E project

Area 9.1 is one of many contracts Weltec has delivered in Ireland’s pharma and bio-pharma and life sciences sectors. Browse more completed projects, or contact the team to talk to our team about your facility.

Bríd Duffy

Procurement Manager

Bríd is the Weltec Procurement Manager with over 20 years’ experience in the M&E Construction Industry. She joined Weltec in 2001, and has gained extensive knowledge in Project Management, Relationship Management and Negotiating Skills across different sectors including Pharmaceutical, Life Sciences, Industrial and Food.  Bríd holds a Bachelor of Business in Industrial Purchasing from ITC and a Masters in Personal and Management Coaching from UCC.

David O'Connor

HR Advancement Manager

David is the HR Advancement Manager and holds a Degree in HR and Level 9 awarded from the Institute of Leadership and Management. He is a self-motivated Human Resources professional with over 20 years’ experience in industrial relations practices and employee relations within the manufacturing and construction industry. Working closely with the senior leadership team in Weltec, David is adept at planning, building relationships, implementing development programs and innovating change that enhance the company’s core values and aid the development of their people.

Eddie Hynes

Commercial Manager CSA/MC

Eddie is the CSA / MC Commercial Manager responsible for managing all commercial aspects of Main Contracting Projects from project estimating, value engineering, advise on procurement route through to final account settlement. Providing clients with real-time cost control and budgeting advice on a range of sectors including Pharmaceutical & Life Sciences. Eddie holds qualifications in Construction Technology and Management, Quantity Surveying and more recently has completed a Level 8 Special Purpose Award in M&E Quantity Surveying.

Trevor McPhillips

Managing Director

Trevor is the Managing Director of Weltec. He holds a degree in Building Services Engineering from CIT and holds an MBA from SETU Waterford. With over 25 years of experience in the M&E construction sector, he leads the implementation of a client-focused strategy encompassing both existing clients and the development of new business. He uses his experience to guide Weltec’s organisational structure to sustainably meet future growth and development goals. Trevor has worked on numerous complex and advanced technology projects in sectors such as Semiconductor, Data centre, Bio-Pharma, Medical Devices, and Food processing.

TJ Phelan

Projects Director

TJ is an IPMA Project Manager with 30+ years experience in the industry. TJ joined the team in 1995. He has been responsible for projects in our key sectors – Pharmaceutical, Life Science, Healthcare and Commercial. TJ has managed and developed teams in both Mechanical and Main Contractor Roles. He is responsible for understanding and managing both internal and external Stakeholder needs.

Lorraine Clooney

Finance Manger

Lorraine is the company Finance Manager with overall responsibility for the FInance Team. Lorraine has worked in finance in the multinational Private Healthcare industry in both the UK and Ireland and she has worked in the Construction industry for the past 15 years. As Finance Manager, her role covers financial reporting, project-specific cash flow reporting, maintaining credit, preparing annual budgets, and tracking budget progress throughout the financial year.

ANTONOV AIRPORT – OSM CARBON WORKSHOP

Airport-situated facility for carbon steel projects. Reconfigurable as necessary

  • 18,000 sqft
  • OSM assembly area
  • Gantry cranes
  • Dock levellers
  • Large secure yard

John Murphy

Quality Director

John is the company Quality Director with overall responsibility for all Quality activities and resources. He is hugely experienced, having worked for many years in the Pharma and Manufacturing before joining Weltec in 2014. He holds qualifications in Chemistry, Quality Assurance, a Lean Six Sigma Black Belt and a Masters in Business Administration.  He has been instrumental in the company’s continuous implementation of new and improved quality standards across all engineering and construction activities. He has also been the key driver in ensuring we fully understand our customer expectations and needs and that we have developed and implemented the quality control processes to meet and exceed these expectations.

Joe McGivney

General Manager, Electrical

Joe is a IPMA certified Project Manager and as General Manager Joe takes a key role in project proposals, project development, construction operations, and communication with all key stakeholders. He applies his extensive engineering and project management experience acquired over his 40 year successful career. He has delivered complex projects across many sectors including Pharmaceutical, Life Sciences, ICT Manufacturing and Healthcare.

James Hackett

EHS Director

James is EHS Director and holds a BSc in Management and a H-Dip in Health, Safety & Welfare at Work from UCC. Working closely with the operations director, general manager and contract managers, James has full responsibility for all EHS activities and resources across the company. James has been instrumental in directing the company to achieving world-class EHS practices, which have been recognised by NISO with the company winning the All Ireland Presidents Safety Award for Large Organisations for the second time in three years, the Bronze Award twice in 4 years and the overall All Ireland Gold Award in 2021. 

Shane Ryan

Operations Director

Shane holds a Bachelors Degree in Engineering from UL and as Operations Director he is centrally involved in the direction and execution of all construction operations. He focuses on assembling multi-disciplinary teams to deliver large-scale complex turnkey projects and creating sustainable ongoing partnerships. He has extensive engineering and project management experience across different sectors including Pharmaceutical, Life Sciences, Industrial and Food.

Gerard O’Leary

CEO

Gerard is the CEO and one of the original founders of Weltec Engineering in Waterford over 24 years ago. He holds a Bachelors Degree in Engineering from CIT and an Honours MBA from UCC. He has over 30 years experience in the engineering and construction industries and has been instrumental in the development of the company into a leading engineering and process contractor.