- Weltec were main contractor, mech contractor & PSCS for the bivv project which involved the remodeling of Fill Finish write up area to a new Compounding Formulation & Thawing Suites at Sanofi.
- Setting out of all new routes and plant within the existing Fill Finish Building Level 3 Plant Room and Thawing area.
- coordination of the entire install including Fabrication of utilities & process pipework on site, in Weltec Workshop & install on site.
- Completion of shutdowns to integrate new services into existing
- The supply, installation, testing and commissioning of the complete general supply and extract systems for both the Fill Finish Level 3 Plantroom and Thawing Area level 1.
- Installation of Mezz Platform in Fill Finish Level 3 Plantroom.
- No disruption to production.
Scope of Works
M & E Services, CSA, MC & PSCS
Client
Sanofi
Value
€1,388,000
Duration
6.5 Months
Architect/Design Certifier
Consulting Engineer
Tandem
Main Contractor
Weltec Engineering