Weltec were appointed as Main Contractor for the UHL Autoclave Enabling Works.
All the external works took place in the Boilerhouse and the Physio roof and all internal works took place in the Autoclave Room (R4314)
Scope
Offsite fabrication of a new plant room and installation on the physio roof at the back of the CSSD building
Installation of a new steam and condensate line from the existing boiler house, to the new plant room and into the autoclave room.
Installation of new steel supports for the pipework and Plantroom.
Installation of new control valves and bypasses in the new plant room.
Installation of lights and sockets to the new plant room.
Installation of handrail around the Physio roof.
Installation of new lights in the autoclave room.
Installation of new steam header and control valves in the Autoclave room.
Installation of bulkhead around the new steam heater and valves.
PSCS roll over this project.
Note: All works in the Autoclave rooms took place at night.